23 février 2024
On January 24, 2024, the Nova Scotia Supreme Court upheld the N.S. Environment Minister’s approval of a proposed windfarm development’s environmental assessment, giving the developer the go-ahead to take the next steps to get the project in the air. The Court’s decision in Folly Lake-Wentworth Valley v. N.S. Minister of Environment illustrates how concerned citizens’ groups are increasingly using court processes to challenge proposed developments – and offers project proponents three practical take-aways to help avoid those challenges.
A developer proposed erecting a 17-turbine windfarm in rural Nova Scotia. The N.S. Minister of Environment conditionally approved the project pursuant to the N.S Environment Act. The approval was based on the developer’s submissions, that included a 260-page project assessment, over 2,700 pages of scientific and other documents and public input and information following consultation with Indigenous groups, the public, and multiple departmental briefings. A citizens’ group applied to the Court for judicial review of the Minister’s approval decision and ultimately, to quash it. But the Court decided the Minister’s decision was reasonable and upheld it:
Reasonable Decision. The Court re-confirmed it’s the decision-maker’s job to assess the scientific evidence on which its decision is based. In a judicial review, the Court’s job is to determine whether the decision-maker’s decision was reasonable: within the range of possible outcomes at which they could reasonably arrive. The Court’s job is not to determine whether that decision was “correct”, whether it was the “best” decision or to substitute its own decision. When legislation gives a body the authority to make a decision, the Court owes that decision-maker deference. And it’s for the party opposing the decision to prove that decision was unreasonable.
Legislative Requirements. The Court also re-confirmed the Minister need only comply with the legislative requirements in reaching their decision. Based on the record, the Minister considered all factors the applicable legislation required them to consider. The Court expressly rejected the citizens’ group contention the Minister didn’t “adequately” consider certain factors, characterizing it as an attempt to apply a correctness – as opposed to reasonableness – standard. The legislation required only that the Minister “consider” the factors; that consideration isn’t required to meet a standard the citizens’ group “or anyone else” might consider “adequate”. The Court did specifically note the legislation’s “polycentric” objectives, including “maintaining the principles of sustainable development” and the balancing exercise it requires.
Approval Conditions. The Court finally re-confirmed the Minister’s approval conditions were reasonable and need not meet any “adequacy” threshold. The Court specifically made the “important point” that the Minister’s approval was conditional on the developer’s obligation to comply with other applicable regulatory requirements and in any event any approval wouldn’t exempt the developer from complying with them.
The Court’s decision offers project proponents three practical take-aways to deal with objections to proposed development by citizens and citizens’ groups.
1. Anticipate Citizen Challenges
Individuals and groups opposing development are increasingly voicing their objections to proposed natural resources developments – and increasingly turning to the courts to try to halt or delay them. Take steps to anticipate and plan for these challenges so you’re best positioned to avoid them and, if you can’t, to respond to them.
2. Read the Legislation Carefully
The specific wording of the legislation and the regulations, if any, under which the relevant government or regulatory authority’s decision is issued is crucial. Read it carefully and ensure you have a solid understanding of what the legislation requires of the decision-maker and the decision-making process so you’re well-prepared.
3. Make Your Submission Thorough
Ensure your submission in support of the decision you seek is robust from the outset. If it lacks any information the applicable legislation requires the decision-maker to consider in making their decision, the decision-maker could either send it back for more information or deny it, both costing you time and money. Or if they approve it and that approval is later challenged in a court, that could form a basis for the court to grant the request to quash or delay the decision.
Please contact your McInnes Cooper lawyer or any member of our Renewable Energy Team @ McInnes Cooper to discuss how we can help you obtain – or defend – your development approval.
13 mai 2026
Ottawa has signalled a rewrite of the federal approvals system for major projects with its May 8, 2026 announcement. While no legislation has yet…
30 avril 2026
If you’re a proponent of a major project in Canada, this update is for you. Recent amendments to Canada’s Competition Act change the ground rules…
15 septembre 2025
Since July 2023, Canada has new rules called the Clean Fuel Regulations. These rules are designed to make transportation fuels (like gasoline and…
26 juin 2025
On May 1, 2025, the Supreme Court of Canada denied leave to appeal in Ontario v. Mathur, a significant climate litigation case that brings youth…
22 janvier 2025
On November 12, 2024, the Hague Court of Appeal quashed the 2021 landmark decision of the Hague District Court in Milieudefensie et al v. Royal Dutch…
26 août 2024
On June 20, 2024, the Canadian Competition Act was amended to specifically make greenwashing claims reviewable conduct. Pressure on Canadian…
22 août 2024
In early April 2024, Nova Scotia’s Energy Reform (2024) Act (Bill 404) passed, marking the beginning of a new direction for Nova Scotia’s energy…
23 février 2024
On January 24, 2024, the Nova Scotia Supreme Court upheld the N.S. Environment Minister’s approval of a proposed windfarm development’s environmental…
1 novembre 2023
On October 13, 2023, the Supreme Court of Canada issued its judicial reference opinion: a significant portion of Canada’s federal environmental…
8 août 2023
We updated this publication on August 10, 2023. The Nova Scotia commercial net-metering regime just took another step toward implementation. In its…
25 janvier 2023
Buzz around the potential of hydrogen as a green energy source has been growing. And the Atlantic Canadian provinces are poised to become a key hub…
10 novembre 2022
Updated August 8, 2023. October 2022 amendments to the N.S. Renewable Electricity Regulations ushered in a new Commercial Net-metering regime in Nova…
24 juin 2022
The New Brunswick Court of Queen’s Bench has issued a court order to stop Indigenous fishers (all apparently members of the Wolastoqey Nation)…
6 juin 2022
The Federal Court’s April 22, 2022 decision in Mowi Canada West Inc. v. Canada (Fisheries, Oceans and Coast Guard) has implications for the fisheries…
3 février 2022
On January 26, 2022, the British Columbia Court of Appeal extended an injunction preventing protesters from interfering with a logging company’s…
10 novembre 2021
On November 5, 2021, the Province of Nova Scotia passed the Environmental Goals and Climate Change Reduction Act. The Act will serve as the framework…
27 juillet 2021
Canadian entities regularly contract with foreign companies to provide services in Canada. To complete its obligations under the contract, the…
1 juin 2021
NOTE: On November 12, 2024, the Hague Court of Appeal quashed the decision of the Hague District Court in Milieudefensie et al v. Royal Dutch Shell…
20 janvier 2021
We updated this publication on July 8, 2022. 2020 was a year filled with challenges, including in the relationship between Indigenous communities,…
22 novembre 2019
The Environmental Emergency Regulations, effected under section 200(1) of the Canadian Environmental Protection Act (CEPA) and in force since August…
7 décembre 2016
Updated February 7, 2024. We live in a world of change. New ideas and new industries are rapidly developing and the list keeps growing: tidal…
9 novembre 2016
The balance between the public’s interest in accessing offshore petroleum resources data and operators’ commercial interests is at the heart of the…
6 juin 2016
Each Provincial government is under the legal duty to consult; the manner in which each carries out its legal duty to consult differs depending on…
2 mai 2016
Updated October 4, 2023. Workplace accidents regularly lead to charges under occupational health and safety (OHS) law. These charges can be against…
19 avril 2016
On April 14, 2016, the Supreme Court of Canada decided that Métis and “non-status Indians” are “Indians” under section 91(24) of the Constitution…
24 mars 2016
When a business responds to a public sector Request for Proposal or Expression of Interest (both of which we’ll refer to as an RFP for these…
9 mars 2016
On January 11, 2016, the Ontario Superior Court of Justice sentenced a front-line supervisor to imprisonment for 3½ years for four counts of criminal…
21 décembre 2015
A practical and current guide created to help you navigate the increasingly important issues surrounding offshore decommissioning and abandonment.…
25 juin 2015
Updated October 4, 2023. Most people know a company itself has occupational health and safety (OHS) obligations and risks corporate liability if it…
26 juin 2014
On June 26, 2014, in its groundbreaking decision on Aboriginal title in Tsilhqot’in Nation v. B.C., the Supreme Court of Canada significantly…
Inscrivez-vous à McInnes-Cooper pour rester au courant de nos informations sur les affaires juridiques, tendances actuelles, les nouvelles, et plus.